Project No.: 2001/005

Issue No.: 1

 

 

 

 

Date: 03 October 2002

 

 

 

 

KCRC East Rail Extension Development

Contract No. HCC-300 and HCC-302

 

 

 

 

Tsim Sha Tsui East Station (HCC-300)

Pedestrian Subway (HCC-302)

 

 

 

 

Impact EM&A Report for September 2002

 

 

 

 

Prepared For

Gammon-Nishimatsu Joint Venture Limited

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


This report has been prepared by Action-United Environmental Services & Consulting with all reasonable skill, care and diligence within the terms of the Agreement with the client, incorporating our General Terms and Conditions of Business and taking account of the resources devoted to it by agreement with the client.

We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above.

This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known. Any such party relies upon the report at their own risk.


Table of Contents

 

1.0       Introduction.. 1

2.0       Project information.. 2

3.0       Status of Environmental Permits and Submissions. 4

4.0       Summary of EM&A Requirements. 6

5.0       Impact Monitoring Results. 11

6.0       Environmental Complaint and Non-Compliance. 19

7.0       Implementation of Mitigation Measures. 22

8.0       Waste Management. 24

9.0       Effluent Discharge and In-house Sampling.. 25

10.0     Environmental Training and Awareness. 25

11.0     Landscape and Visual Impact. 25

12.0     IEC and CET Site Audit. 26

13.0     Archaeological/Cultural Heritage Monitoring.. 27

14.0     Land Contamination Assessment. 27

15.0     Forecast and Schedule. 27

16.0     response to Comments from EPD/KCRC/IEC.. 27

17.0     Conclusion.. 28

 

List of Tables

Table 2-1                  Summary of Major Construction Activities in September 2002

Table 3-1                  Summary of License/Permit Status

Table 3-2                  Summary of Document Submissions

Table 4-1                  Locations of Air Quality Monitoring Stations

Table 4-2                  Action/Limit Levels for 24-Hr TSP Monitoring

Table 4-3                  Action/Limit Levels for 1-Hr TSP Monitoring

Table 4-4                  Locations of Regular Noise Monitoring Stations

Table 4-5                  Locations of Continuous Noise Monitoring Stations

Table 4-6                 Action/Limit Levels for Regular and Continuous Noise Monitoring

Table 4-7                 Distance Correction for Noise Monitoring Results

Table 5-1                  Summary of 1-Hr TSP Monitoring Results

Table 5-2                  Summary of 24-Hr TSP Monitoring Results

Table 5-3                  Summary of Regular Noise Monitoring Results

Table 6-1                  Summary of Complaint Statistics

Table 6-2                  Summary of Environmental Complaint

Table 6-3                  Summary of CPAR Statistics

Table 8-1                  Summary of Waste Disposal in September 2002

 

List of Appendices

Appendix A              Project site layout for HCC-300 and HCC-302

Appendix B               Key personnel contact list

Appendix C               Maps showing environmental monitoring stations

Appendix D              Graphical presentations of 1-Hr TSP monitoring results in September 2002

Appendix E               Graphical presentations of 24-Hr TSP monitoring results in September 2002

Appendix F               Graphical presentations of regular noise monitoring results in September 2002

Appendix G               Graphical presentations of CNM results in September 2002

Appendix H              Equipment calibration certificates

Appendix I                Summary of CPAR Status

Appendix J                Summary of mitigation measures implementation status

Appendix K              Report on Champion Tree No. 251

Appendix L               Schedule of EM&A schedule in upcoming 3 month (Oct, Nov and Dec 02)

Appendix M              IEC comment response form

 

Executive Summary

ES.01  Gammon-Nishimatsu Joint Venture Limited (hereafter ¡§the JV¡¨) was awarded the Contracts of East Rail Extensions Tsim Sha Tsui East (TST East) Rail development project HCC-300 and HCC-302 by the Kowloon-Canton Railway Corporation (KCRC).

 

ES.02  Action-United Environmental Services and Consulting (AUES) was commissioned by the JV to implement an Environmental Monitoring and Audit (EM&A) program in accordance with the approved EM&A Manual to maintain acceptable environmental quality throughout the construction period.

 

ES.03  This monthly EM&A report summarizes the monitoring results and audit findings of the EM&A program in the reporting month of September 2002.

 

Key Construction Progress

ES.04  The major construction activities in this reporting month for both contracts HCC-300 and HCC-302 include sheet piling, excavation work and road diversion for utilities. Details of the construction work undertaken in this reporting month are summarized in Section 2.2.

 

Environmental Monitoring and Audit Progress

ES.05  The monthly EM&A program was undertaken in accordance with the approved TST EM&A manual and relevant contractual requirements.  A summary of the monitoring activities in this reporting month is listed below:

Ÿ           1-Hr TSP Monitoring

  90 Occasions

Ÿ           24-HR TSP Monitoring

  30 Occasions

Ÿ           Regular Noise Monitoring

  35 Occasions

Ÿ           Continuous Noise Monitoring

  68 Occasions

Summary of Environmental Exceedance

ES.06  A summary of monitoring exceedance and the level of compliance in this reporting month is presented as follows:

 

Env. Quality

Parameters

% Compliance

Investigation & Corrective Actions

Air Quality

1-Hr TSP

100%

Not required for 100% compliance

24-Hr TSP

100%

Not required for 100% compliance

Noise

Regular Noise

100%

Not required for 100% compliance

CNM

100%

Not required for 100% compliance

 

Effluent Discharge and In-house Monitoring Program

ES.07  Site effluent is regularly sampled and analyzed according to the requirements of the wastewater discharge permit issued by EPD.

 

Restricted-Hour Noise Monitoring

ES.08  No construction was undertaken during restricted hours in this reporting month and no restricted-hour noise monitoring was required.


Site Inspection and Audits

ES.09  Environmental audits and inspections were conducted in this reporting month. A summary of dates of the audits and inspections carried out by the concerned parties are presented as follows:

Concerned Parties

Dates of Audit/Inspection

CET

6, 10, 20 and 27 September 2002

IEC/KCRC

27 September 2002

 

ES.10  The IEC¡¦s and CET¡¦s audit findings are summarized in the following table with the corrective actions/mitigation measures implemented or proposed by the JV.

 

Item

IEC/CET

Date Recorded

Key Audit Findings

Proposed Actions/Mitigation Measures

HCC-300

1

IEC

27 Sept 02

Wing On Plaza (near Salisbury Road): The sedimentation system should be maintained properly to avoid any leakage of chemical (flocculent). The sediment should be removed regularly.

Site staff has been reminded to regularly maintain the sedimentation system with sediment deposits removed.

 

2

IEC

27 Sept 02

Wing On Plaza (D4, D5, D7 & D8): Site exit should be free from dust/mud debris.

The work sites are metal decked. Site staff has been reminded to regularly clean up the soil debris on the deck.

3

IEC

27 Sept 02

Wing On Plaza: Breaking without watering was observed.

Site staff has been reminded to apply watering in the course of breaking to control dust emissions.

4

IEC

27 Sept 02

Middle Road Playground: Stockpiles should be watered whenever necessary.